Timeline for the HSR Project. The timeline can be viewed in the Context Sensitive Solutions (CSS) Toolkit on the HSRA site. See this link for the timeline. Further understanding of the purpose of the CSS toolkit can be found elsewhere on this site along with other public input opportunities. See the side bar for Public Input - to High Speed Rail Authority. Note the timeline as it gives you an idea of where we are in the process. The timeline is subject to change, but at this time is being driven by the stimulus funds requirement that construction begin on the Peninsula section by 2012.
As of April 2010 engineering for the Peninsula section is at about 3-5% engineering. The project is expected to be at about 15% engineering by fall. At 15% engineering, we will have construction details, in other words how the different alternatives might be constructed, including how they will keep Caltrain operational during construction. Some basic understanding of the sequencing of the construction is described in the AA appendixes.